Our team SK (SK Comsa) successfully worked in the replacement of the Shiploader in a 35 day period record time (shutdown enclosed), according to the international experience that establishes that this task takes around four to five months.
An auxiliary dock mounted from the sea is used to execute the dismantling and installation of new equipment, maneuvers and systems of pulling and transfering. All the engineering of rigging was made by the Special Maneuver Unit of SK, including high tonnage instances to mount around 530,000 miles of structures from the sea.